• DAPRMap
  • home Home
  • call Contact Us
DAPR 2023
Distribution Annual Planning Report Map 2023

Disclaimer

The DAPRM (Distribution Annual Planning Report Map) is an interactive geospatial map that has been developed to provide indicative information regarding Energex’s regulated network topology, forecast loads and capacities, and network constraints. The DAPRM is an information service available to the public.

Users of this service must acknowledge and accept that:

  • The information obtained from the DAPRM is intended as general in nature, may be based on assumptions that change with time and may not necessarily be complete. Information contained in, or obtained from, the DAPRM should not be relied upon.
  • Energex makes no representation or warranty as to the accuracy or completeness of any information obtained from the DAPRM. The DAPRM is not a substitute for independent advice and research.
  • Energex does not accept any responsibility for any loss or damage, however caused, which any person or entity may suffer in connection with the information contained in, or obtained from, the DAPRM.

Note

Grayed out layers are only available at certain zoom levels.

Note

  • Data applies to the current year only. Data will be updated annually in line with the release of the Distribution Annual Planning Report (DAPR).
  • Some data layers may need to be enabled, or are only available at certain zoom levels. Please see for Layer options

About this map

This mapping portal forms part of our Distribution Annual Planning Report (DAPR) (5.2 MB) and presents:

  • the topology of our regulated network, including transmission network connection points, substations and sub-transmission network
  • forecast loads for transmission network
  • connection points, forecast loads and capacity information for each of our substations and sub-transmission feeders
  • joint owned connection points
  • sub-transmission & substation constraints that are forecast to emerge in the next 5 years.

As a Distribution Network Service Provider (DNSP), we are required to publish this information under Rule 5.13 and Schedule 5.8 of the National Electricity Rules (NER).

Forecast Information

Bulk Supply Substations Load Forecast (1.8MB)

Peak Load Forecast and Capacity Tables

These tables show information about the substation’s customer category, transformer capacity, including emergency cyclic capacity and normal cyclic capacity, load at risk, and the compliance of each substation with its security standard.

Definition of Terms - Bulk Supply Point Capacity and Forecast Tables

Peak Risk Period

The time period over which the load is highest (Day/Night).

NCC Rating (MVA)

Normal Cyclic Capacity - the total capacity with all network components and equipment in service.

Contracted non-network (MVA)

The amount of embedded generation and contracted curtailed demand management capacity available within the supply area of a substation during peak times. The impacts of these have been incorporated into the load forecasts. Solar PV connections are not included in the reported figure.

10 PoE Load (MVA)

Peak load forecast with 10% probability of being exceeded (one in every 10 years will be exceeded). Based on normal expected growth rates and weather corrected starting loads.

LARn (MVA)

Security standard load at risk under system normal condition, expressed in MVA.

LARn (MW)

Security standard load at risk under system normal condition, expressed in MW.

Power Factor at Peak Load

Compensated power factor at 50 PoE Load.

ECC Rating (MVA)

Emergency Cyclic Capacity – the long term firm delivery capacity under a single contingent condition. The maximum permissible peak emergency loading for a given load cycle that an item of plant can supply for an extended period of time without unacceptable damage.

50 PoE Load (MVA)

Peak load forecast with 50% probability of being exceeded (one in every two years will be exceeded). Based on normal expected growth rates & weather corrected starting loads.

Hours PA > 95% Peak Load

The amount of load greater than 95% 50 PoE Load.

Raw LAR (MVA)

The amount of load exceeding ECC rating. (Load – ECC Rating)

2-Hour Rating (MVA)

Two Hour Emergency Capacity (2HEC) – the short term or firm delivery capacity under single contingency conditions.

Auto Trans Avail (MVA)

SCADA or automatically controlled load transfers that can be implemented within one minute.

Remote Trans Avail (MVA)

Load transfers that can be implemented through SCADA switching procedures by the network control officer. It is assumed that this can generally be achieved within 30 minutes.

Manual Trans Avail (MVA)

Load transfers can also be deployed via manually controlled switchgear locally by field staff.

Mobile Plant Avail (MVA)

The capacity of mobile substation or mobile generation that can be deployed within the timeframe and capacity prescribed by the security standard.

POPS

Plant Overload Protection Scheme (POPS) consists of several applications which continuously monitor specific items of plant for overload conditions. If overload conditions are detected and validated, POPS will initiate predefined actions in order to relieve the overload condition.

LARc (MVA)

Security standard load at risk for single contingent conditions.

LARc (MW)

Estimated generation / load reduction required to defer the forecast system limitation. This is the security standard load at risk under single contingency condition, expressed in MW.

Customer Category

For security standard application, the general type of customer a substation or feeder supplying the area.

For further information, please refer to Appendix D of Energex Distribution Annual Planning Report.

The tables show information for Jointly Owned Substations in the Energex network. These are typically substations that Powerlink own, and are Transmission Connection Points to the Energex network. It should be noted that for Jointly Owned substations, Energex typically only owns the switchgear at the connection point, and as such the Energex ratings will not reflect the rating of upstream equipment not owned by Energex. For further information, please refer to Appendix D of Energex Distribution Annual Planning Report.

Zone Substations Load Forecast (13.7MB)

Peak Load Forecast and Capacity Tables

These tables show information about the substation’s customer category, transformer capacity, including emergency cyclic capacity and normal cyclic capacity, load at risk, and the compliance of each substation with its security standard.

Definition of Terms - Zone Substation Capacity and Forecast Tables

Peak Risk Period

The time period over which the load is highest (Day/Night).

NCC Rating (MVA)

Normal Cyclic Capacity - the total capacity with all network components and equipment in service.

Contracted non-network (MVA)

The amount of embedded generation and contracted curtailed demand management capacity available within the supply area of a substation during peak times. The impacts of these have been incorporated into the load forecasts. Solar PV connections are not included in the reported figure.

10 PoE Load (MVA)

Peak load forecast with 10% probability of being exceeded (one in every 10 years will be exceeded). Based on normal expected growth rates and weather corrected starting loads.

LARn (MVA)

Security standard load at risk under system normal condition, expressed in MVA.

LARn (MW)

Security standard load at risk under system normal condition, expressed in MW.

Power Factor at Peak Load

Compensated power factor at 50 PoE Load.

ECC Rating (MVA)

Emergency Cyclic Capacity – the long term firm delivery capacity under a single contingent condition. The maximum permissible peak emergency loading for a given load cycle that an item of plant can supply for an extended period of time without unacceptable damage.

50 PoE Load (MVA)

Peak load forecast with 50% probability of being exceeded (one in every two years will be exceeded). Based on normal expected growth rates & weather corrected starting loads.

Hours PA > 95% Peak Load

The amount of load greater than 95% 50 PoE Load.

Raw LAR (MVA)

The amount of load exceeding ECC rating. (Load – ECC Rating)

2-Hour Rating (MVA)

Two Hour Emergency Capacity (2HEC) – the short term or firm delivery capacity under single contingency conditions.

Auto Trans Avail (MVA)

SCADA or automatically controlled load transfers that can be implemented within one minute.

Remote Trans Avail (MVA)

Load transfers that can be implemented through SCADA switching procedures by the network control officer. It is assumed that this can generally be achieved within 30 minutes.

Manual Trans Avail (MVA)

Load transfers can also be deployed via manually controlled switchgear locally by field staff.

Mobile Plant Avail (MVA)

The capacity of mobile substation or mobile generation that can be deployed within the timeframe and capacity prescribed by the security standard.

POPS

Plant Overload Protection Scheme (POPS) consists of several applications which continuously monitor specific items of plant for overload conditions. If overload conditions are detected and validated, POPS will initiate predefined actions in order to relieve the overload condition.

LARc (MVA)

Security standard load at risk for single contingent conditions.

LARc (MW)

Estimated generation / load reduction required to defer the forecast system limitation. This is the security standard load at risk under single contingency condition, expressed in MW.

Customer Category

For security standard application, the general type of customer a substation or feeder supplying the area.

For further information, please refer to Appendix D of Energex Distribution Annual Planning Report.

110 kV and 132 kV Feeders Summer Forecast (511KB)
110 kV and 132 kV Feeders Winter Forecast (498KB)

Peak Load Forecast and Capacity Tables

These tables show information about the feeder capacity, load at risk, and the compliance of each feeder with its security standard.

Interconnected or feeders that supply multiple customers are examined in the following tables. Feeders exclusively supplying a customer owned substation or dedicated to a customer are not included in these tables.

Definition of Terms - Feeder Capacity and Forecast Tables

NCC Rating (A)

Normal Cyclic Capacity - the total capacity with all network components and equipment intact.

10 PoE Load (A)

Peak load forecast with 10% probability of being exceeded (one in every 10 years will be exceeded). Based on normal expected growth rates and weather corrected starting loads.

Power Factor (System Normal)

Lowest power factor along the feeder at 10 PoE Peak Load.

LARn (A)

Security standard load at risk under system normal condition, expressed in Amps.

LARn (MW)

Security standard load at risk under system normal condition, expressed in MW, assuming the nominal system voltages and lowest power factor.

ECC Rating (A)

Emergency Cyclic Capacity – the long term firm delivery capacity under single contingency conditions.

50 PoE Load (A)

Peak load forecast with 50% probability of being exceeded (one in every two years will be exceeded). Based on normal expected growth rates & weather corrected starting loads.

Hours PA > 95% Peak Load

The forecast number of hours per annum where the load exceeded 95% of the peak 50 PoE demand.

Raw LAR (A)

The amount of load exceeding ECC rating. (Load – ECC Rating)

2-Hour Rating (A)

Two Hour Emergency Capacity (2HEC) – the short term firm delivery capacity under single contingency conditions.

Auto Trans Avail (A)

SCADA or automatically controlled load transfers that can be implemented within one minute. A blank entry indicates that this type of transfer is not considered as available in the evaluation of security standard compliance.

Remote Trans Avail (A)

Load transfers that can be implemented through SCADA switching procedures by the network control officer. It is assumed that this can generally be achieved within 30 minutes. A blank entry indicates that this type of transfer is not considered as available in the evaluation of security standard compliance.

Manual Trans Avail (A)

Load transfers can also be deployed via manually controlled switchgear locally by field staff. A blank entry indicates that this type of transfer is not considered as available in the evaluation of security standard compliance.

POPS

Plant Overload Protection Scheme (POPS) consists of several applications which continuously monitor specific items of plant for overload conditions. If overload conditions are detected and validated, POPS will initiate predefined actions in order to relieve the overload condition.

Mobile Gen Reqd (A)

The amount of generation required under the contingency, capped at the maximum MVA allowable under the security standard requirements.

LARc (A)

Security standards load at risk under single contingency condition, expressed in Amps.

LARc (MW)

Estimated generation / load reduction required to defer the forecast system limitation. This is the security standard load at risk under single contingency condition, expressed in MW, assuming the nominal system voltages and the lowest power factor on the feeder under system normal condition.

Customer Category

For security standard application, the general type of customer a 110kV, 132kV or 33kV feeder is supplying.

Qualification on the information provided - for a given feeder:
  • If there is no Raw LAR forecast over the period reported:
    • Forecast:
      • 10 PoE forecast is shown;
      • 50 PoE is not shown; and
      • shown as blank for feeders not normally supplying load.
    • Rating:
      • NCC rating is shown; and
      • ECC and 2HEC ratings are not shown.
    • Transfers:
      • no details shown.
  • If there is forecast Raw LAR in any year over the period reported:
    • Forecast:
      • 10 PoE is shown in all years; and
      • 50 PoE is shown in years when Raw LAR is forecast and shown as blank in years where no Raw LAR is forecast.
    • Rating:
      • NCC is shown in all years; and ECC and 2HEC are shown in years when Raw LAR is forecast and shown as blank in years where no Raw LAR is forecast.
    • Transfers – Auto, Remote and Manual:
      • where available, details are provided in years where Raw LAR is forecast and shown as blank in years where no Raw LAR is forecast.
    • Load at Risk:
      • where available, details are provided in years where Raw LAR is forecast and shown as blank in years where no Raw LAR is forecast.

For further information, please refer to Appendix E of Energex Distribution Annual Planning Report.

33 kV Feeders Summer Forecast (219KB)
33 kV Feeders Winter Forecast (272KB)

Peak Load Forecast and Capacity Tables

These tables show information about the feeder capacity, load at risk, and the compliance of each feeder with its security standard.

Interconnected or feeders that supply multiple customers are examined in the following tables. Feeders exclusively supplying a customer owned substation or dedicated to a customer are not included in these tables.

Definition of Terms - Feeder Capacity and Forecast Tables

NCC Rating (A)

Normal Cyclic Capacity - the total capacity with all network components and equipment intact.

10 PoE Load (A)

Peak load forecast with 10% probability of being exceeded (one in every 10 years will be exceeded). Based on normal expected growth rates and weather corrected starting loads.

Power Factor (System Normal)

Lowest power factor along the feeder at 10 PoE Peak Load.

LARn (A)

Security standard load at risk under system normal condition, expressed in Amps.

LARn (MW)

Security standard load at risk under system normal condition, expressed in MW, assuming the nominal system voltages and lowest power factor.

ECC Rating (A)

Emergency Cyclic Capacity – the long term firm delivery capacity under single contingency conditions.

50 PoE Load (A)

Peak load forecast with 50% probability of being exceeded (one in every two years will be exceeded). Based on normal expected growth rates & weather corrected starting loads.

Hours PA > 95% Peak Load

The forecast number of hours per annum where the load exceeded 95% of the peak 50 PoE demand.

Raw LAR (A)

The amount of load exceeding ECC rating. (Load – ECC Rating)

2-Hour Rating (A)

Two Hour Emergency Capacity (2HEC) – the short term firm delivery capacity under single contingency conditions.

Auto Trans Avail (A)

SCADA or automatically controlled load transfers that can be implemented within one minute. A blank entry indicates that this type of transfer is not considered as available in the evaluation of security standard compliance.

Remote Trans Avail (A)

Load transfers that can be implemented through SCADA switching procedures by the network control officer. It is assumed that this can generally be achieved within 30 minutes. A blank entry indicates that this type of transfer is not considered as available in the evaluation of security standard compliance.

Manual Trans Avail (A)

Load transfers can also be deployed via manually controlled switchgear locally by field staff. A blank entry indicates that this type of transfer is not considered as available in the evaluation of security standard compliance.

POPS

Plant Overload Protection Scheme (POPS) consists of several applications which continuously monitor specific items of plant for overload conditions. If overload conditions are detected and validated, POPS will initiate predefined actions in order to relieve the overload condition.

Mobile Gen Reqd (A)

The amount of generation required under the contingency, capped at the maximum MVA allowable under the security standard requirements.

LARc (A)

Security standards load at risk under single contingency condition, expressed in Amps.

LARc (MW)

Estimated generation / load reduction required to defer the forecast system limitation. This is the security standard load at risk under single contingency condition, expressed in MW, assuming the nominal system voltages and the lowest power factor on the feeder under system normal condition.

Customer Category

For security standard application, the general type of customer a a 110kV, 132kV or 33kV feeder is supplying.

Qualification on the information provided - for a given feeder:
  • If there is no Raw LAR forecast over the period reported:
    • Forecast:
      • 10 PoE forecast is shown;
      • 50 PoE is not shown; and
      • shown as blank for feeders not normally supplying load.
    • Rating:
      • NCC rating is shown; and
      • ECC and 2HEC ratings are not shown.
    • Transfers:
      • no details shown.
  • If there is forecast Raw LAR in any year over the period reported:
    • Forecast:
      • 10 PoE is shown in all years; and
      • 50 PoE is shown in years when Raw LAR is forecast and shown as blank in years where no Raw LAR is forecast.
    • Rating:
      • NCC is shown in all years; and ECC and 2HEC are shown in years when Raw LAR is forecast and shown as blank in years where no Raw LAR is forecast.
    • Transfers – Auto, Remote and Manual:
      • where available, details are provided in years where Raw LAR is forecast and shown as blank in years where no Raw LAR is forecast.
    • Load at Risk:
      • where available, details are provided in years where Raw LAR is forecast and shown as blank in years where no Raw LAR is forecast.

For further information, please refer to Appendix E of Energex Distribution Annual Planning Report.

General Information

  • Right to information
  • Terms of use
  • Privacy policy
  • Sitemap
  • Right to Information
  • Terms of Use
  • Privacy
  • Sitemap
  • Copyright © Energex