We understand that time is of the essence when you’re in the field, and having quick access to accurate information can make all the difference. To better assist you, below are a few of the most common queries and their answers from the Electrical Contractors Hotline:
Overhead Point of Attachment (POA)
- Is the POA in a compliant location?
- Is the service line crossing a neighbouring property?
- Does the service line meet the minimum clearance requirements?
In these cases, please refer to clause 6.4 and clause 6.7 in the QECM.
If further clarification is required, an Enquiry for a Point of Attachment can be submitted via the Electrical Partners Portal.
EV Supply Equipment (EVSE)
Where a customer’s electrical installation is 100 amps per phase or less, and a load, such as EVSE is installed at a premises that is either:
- greater than 20 amps single phase; or
- 40 amps three-phase,
that load must be under Active Device Management.
In these cases, please refer to the following clauses in the QECM.
- 8.5.2
- 8.10
- 8.14
- 10.6.5
- Drawing QCD08-01
- Drawing QCD08-02
For further information and to assist you in submitting an Electrical Work Request (EWR) correctly for EVSE in our Electrical Partners Portal, we have developed a detailed guide including screenshots located on our websites:
For any Queensland Electricity Connection Manual (QECM) enquiries, you can use our QECM query call back request webform. The webform allows you to submit your queries and concerns directly to our support team through an easy-to-use online platform at the links below:
We encourage Electrical Contractors to use the QECM query call back request webform for all queries and concerns. By doing so, you will not only help us prioritise urgent matters but also contribute to more efficient and effective customer support.
If you experience any issues with the webform or have any further feedback, please contact us via: qecmtechadvice@energyq.com.au